SMARTWARE – certified low Energy – passive house office building

Panel: 8. Buildings: technologies and systems beyond energy efficiency

Authors:
Marius Soflete, Inginerie Creativa, Romania
Dragos-Ionut Arnăutu, Passive House Institute, Germany

Abstract

Designed and built in less than 1 year - from the first sketch to moving in - the new headquarters of the Romanian company SmartWare, Oradea, is the first office building in the country to be designed and certified as Low Energy Passive House. The headquarters' average energy consumption is less than 30% of the amount of energy used by a generic office building made in recent years.

Besides being highly energy-efficient, the building is also made of materials with low impact on the environment. The structure is made entirely of CLT - a premiere in Romania. Its foundations are laid on a 40 cm thick glassfoam gravel bed, with thermal insulation role, made entirely of recycled glass.

The assembly of the structure was completed in 44 working days and the entire execution in less than 300 days. The total floor area is 2380 square meters, just ground level, serving as working space for 250 IT employees. One of the major challenges of the project was to achieve the passive-house airtightness level, while efficiently ventilate all the server machines.

The final energy parameters of the building are:

Energy required for heating: 27 kwh/m2year

Thermal load for heating: 18 W/m2

Energy required for cooling: 18 kwh/m2year

Thermal load for cooling: 15W/m2

Airtightness: n50=0.301/h

Primary energy: 317 kwh/m2year

The purpose of the presentation is to describe the design experience and to bring up the challenges raised by building and implementing in Romania the first highly energy-efficient office building.